Obama Center Hits $1B as Subs Wait on Pay: Protect Your Claim

The Obama Presidential Center campus is now projected at $1 billion, and trade contractors say they have not been told the new money will settle liens. Here is what subs should check in their contracts and notice calendars now.

FieldNews Staff|
Editorial image: industry general - Obama Center Hits $1B as Subs Wait on Pay: Protect Your Claim

Obama Center Hits $1B as Subs Wait on Pay: Protect Your Claim

If you are a trade contractor on a tiered job where the owner says it has no contract with you, the Obama Presidential Center is a live example of how a payment dispute can outlast the schedule. The campus budget has grown past $1 billion, and subs on the project say they are still waiting on settlements. ENR reports that the trade contractors told it they were not informed that any of the latest $91 million cost increase would go toward resolving liens and other legal actions against the Obama Foundation and its contractors.

Background

ENR reports that the Chicago campus, owned by the nonprofit Obama Foundation, is now expected to cost about $1 billion, more than twice the original $350 million price tag. The budget rose to $500 million when design was completed in 2017, then to $850 million in early September. The latest foundation filing puts the projection about $91 million above the September figure of $909 million. That figure excludes $123 million in publicly financed infrastructure improvements.

The foundation attributes the increase to added construction scope, public art and insurance. The added scope includes the 60,000-sq-ft Home Court basketball center, which ENR says was built by Elevate Design Builders Group, a joint venture of Bowa Construction and AECOM Hunt Construction. Lakeside Alliance, the Turner-led joint venture that built the main Obama Presidential Center building, says its costs have not increased since it finished early last year.

The foundation says it has no outstanding disputed charges with Lakeside and no direct legal agreements or contracts with Lakesideโ€™s subcontractors. It also says change orders are very common on projects of this scale with a major architect. It did not immediately answer ENRโ€™s questions about higher costs on the Elevate contracts.

Project stage: the main building is complete and the foundation says it is planning additional capital improvements. The source does not say how many subs have filed liens, in what amounts, or which trades are affected.

Analysis

The most important detail for field companies is the gap between the budget headline and the payment reality. A $91 million increase sounds like fresh money for the people still owed, but the foundation attributes it to scope, art and insurance, and the subs say nobody told them any of it is earmarked for lien resolution. A rising owner budget does not mean unpaid subs get paid. Money flows through contracts, and the foundation says it has none with Lakesideโ€™s subs.

That position sharpens a structural problem. When the owner points to the GC and the GC says its numbers are settled, a sub in the lower tier has two leverage points left: the statutory remedies attached to the property and the notice record it built during the job. Both depend on paperwork and deadlines, not on the size of the budget. A sub that waits for the owner and GC to reconcile can lose its leverage while they do. (The source does not describe the legal mechanics on this project, so treat what follows as general practice to confirm with counsel.)

The change-order language from the foundation also matters. โ€œChange orders are very commonโ€ is an accurate statement of industry reality, and it is also a reminder that scope growth is where payment disputes start. The Home Court, the art and the insurance cost all sit outside the original building scope. Subs who picked up added work on a job like this are the ones most exposed if the scope was directed verbally, priced late or never papered.

The split between two contractor teams adds a second risk. Lakeside says its costs are flat, while the foundation has not explained cost growth on the Elevate side. A sub working for one team cannot assume the other teamโ€™s budget picture applies to it. Ask your own contracting party, in writing, where your account stands.

What It Means for Subcontractors

  • Pull your subcontract this week and read the payment clause. Your project manager and construction attorney should flag any pay-if-paid or pay-when-paid language, the stated payment timeline after GC receipt, and any limit on claims against the owner. These terms decide whether the GC can lawfully hold your money while the owner and GC argue.
  • Calendar your lien and notice deadlines from your last day of work. Have counsel confirm the deadline under the lien statute of the state where the job sits, and any preliminary notice you were required to send. If you worked on added scope, confirm the clock for that work separately. Missing the filing window is the one mistake that cannot be fixed later.
  • Send written notice to the owner as well as your GC. The Foundation says it has no direct contract with Lakesideโ€™s subs. A dated, documented notice to the owner of record creates a paper trail that a GC-only email chain does not.
  • Check your prompt-payment rights. Ask counsel which state prompt-payment statute applies, what interest or remedy it allows, and whether it requires a written payment demand before it applies. Send that demand now if you are past due.
  • Audit every change order and directive. On any job with scope growth like Home Court, art or insurance adds, confirm that each added task has a signed change order, a price and a time adjustment. For verbal directives, send a written confirmation within days and keep it in the project file.
  • Hold back unconditional lien waivers until funds clear. Use conditional waivers tied to a specific payment amount and date range. Do not sign a final release as part of a settlement until your attorney has read the language on reserved claims.
  • Ask your GC in writing whether any part of the new owner funding is allocated to your claim. If the answer is no, you have a documented basis for escalating. If it is yes, get the amount and the payment date in the reply.
  • On new bids, ask who your contracting party is and what payment security exists. For any added-scope package on a large private-owner project, request project funding and payment security details before mobilizing, and price the delay risk if you cannot get them.

Sources

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

Job Costing for Field Service Companies: How to Know If You're Actually Making Money

A practical job costing guide for oilfield and construction subcontractors. Track labor, equipment, and materials per job to find profit leaks and bid smarter.

Read the guide โ†’

More from Illinois

All coverage โ†’
Follow FieldNews
A community project byAimsio