191 GW of Data Center Load at Risk in TX, OH, GA After Midterms
An estimated 191 GW of planned data center capacity faces new risk after the midterms, with exposure concentrated in Texas, Ohio and Georgia, per an Orennia report shared with Utility Dive.
Market Impact
Orennia says incoming Democratic governors in all three states campaigned on pausing or restricting construction. Texas accounts for nearly half of U.S. data center pre-construction, so a statewide approval freeze would hit the national buildout hard. Gov. Greg Abbott paused new data center interconnections over the summer pending an audit of the queue. He then lost his reelection bid to Democrat Gina Hinojosa, who has pledged to keep pressure on the industry. Of the 46 municipal ballot measures Bloomberg tracked on data center development, nearly all ended in restrictions, moratoriums or bans.
Orenniaโs ERCOT scenario assumes 20% of projected data center demand fails to materialize. In that case, solar and wind average wholesale revenue falls 38% and 37%, respectively, and implied gas heat rates drop 39%. In PJM, delaying half of planned data center buildout by two years could cut four-hour battery arbitrage spreads by 16%.
Stephen Rose, CEO of Render Networks, expects a โpause and necessary shakeout.โ โFully permitted projects with real capital will keep moving,โ he said. โThe speculative end takes the hit: developers land-banking without firm power, and the contractors who staffed up for projects that wonโt break ground.โ He pointed to AEP Ohioโs large-load tariff, approved in July 2025. It requires new data centers above 25 MW to pay for at least 85% of requested capacity for up to 12 years, with exit fees and financial guarantees. The utilityโs pipeline then fell from more than 30 GW to about 13 GW.
Andy Roehr of Baker Tilly expects developers to redirect rather than cancel. He notes they typically evaluate three to five sites at once.
What It Means for Subcontractors
- Electrical and utility-interconnect subs in TX, OH and GA: Pull your contracts on data center backlog and read the termination-for-convenience, demobilization and payment-timing clauses. Roseโs warning is aimed at contractors who staffed up for sites without firm power. Confirm each owner has a secured power path before you add crews.
- Civil and site-prep crews: Rose cited Louisianaโs 2025 BEAD delays, where service providers carried equipment and crew costs while approvals stalled. The hit landed on โlocal drilling, civil and fiber contractors.โ Push for milestone billing and paid standby on speculative-load sites, especially in Texas.
- Ohio bid desks: Projects above 25 MW now sit behind AEP Ohioโs 85% minimum-payment tariff, with exit fees and guarantees. Those owners have financial skin in the game. Work tied to the roughly 17 GW that dropped out of the AEP Ohio pipeline (from 30+ GW to about 13 GW) is the higher-risk backlog to review.
- Estimators and procurement: Roehr says changing demand could reprice everything from gas turbines and processor racks to construction costs. Add escalation language to quotes now and avoid fixed-price commitments on long-lead equipment without owner deposits.
- Business development: Roehr expects projects to shift to โless optimal sitesโ in friendlier jurisdictions, with states bidding for them. Build relationships with developers in less restrictive states so you can follow the work if Texas, Ohio or Georgia projects move.