Grid Runs at 40% to 60% Use, BNEF Houston Panelists Say
Utility Dive reports that panelists at the BNEF Houston Summit put grid utilization at 40% to 60% and argued utilities can connect large loads faster by using flexibility tools before building new lines.
Market Impact
Tyler Norris, head of market innovation for energy and power at Google, said the โreal whitespaceโ is enabling non-firm transmission service. He pointed to an Aligned Data Centers and Portland General Electric deal in Hillsboro, Oregon. The developer agreed to deploy a 31 MW/62 MWh battery for a 72-MW data center, which let it bypass what would otherwise have been a fully firmed network upgrade. โWe will see moreโ of these arrangements, Norris said.
Utilization data backs the argument. Grid Strategies puts the systemwide load factor at about 60%, heading to 66% by 2030. Dominion Energyโs Virginia subsidiary reported that its distribution grid averages a 41% load factor and peaks just under 80% utilization. Its transmission systemโs median facility utilization is about 33%, though individual facilities can approach or exceed rated capacity during outages, demand peaks or significant power transfers.
Other panelists focused on tools and targets. Dave Berry, CEO of Cloverleaf Infrastructure, said Remedial Action Schemes, common in the Western Interconnection, already add headroom, but they can harm customers in other areas when they curtail generation or load. Arushi Sharma Frank, an advisor to the Utilize Coalition, said AI tools can help planners and operators see capacity that was previously invisible. NRGโs Jessica Hogle said the Texas-based company aims to deliver 25 GW of demand response, storage and virtual power plant capacity by 2035.
The panel did not discuss reconductoring or specific hardware upgrade programs. The takeaways below are our reading of the figures.
What It Means for Subcontractors
- Electrical and E&I: Flexibility deals need hardware. The Hillsboro agreement paired a 72-MW load with a 31 MW/62 MWh battery, a battery about 43% of the loadโs size. Storage interconnection, controls and protection work is the scope to pursue with developers and utilities using this model.
- Transmission line and substation crews: Dominionโs 33% median transmission utilization, with some facilities near or above rating during peaks, points to targeted fixes at constrained facilities rather than blanket rebuilds. Position for spot upgrades, not corridor-wide programs.
- New-build civil and line crews: Where non-firm service replaces a โfully firmed network upgrade,โ the upgrade may never be built. Review your backlog for network upgrades tied to large-load interconnections, especially data center projects, since those are the ones at risk of deferral.
- Storage, DR and VPP installers: NRGโs 25 GW by 2035 target covers demand response, storage and virtual power plant capacity. That is a long-dated installation pipeline for electricians and controls techs. Contact NRGโs procurement team in Texas now to get on bidder lists.
- Protection and controls specialists: Berry said Remedial Action Schemes work but require aligning all stakeholders. Utilities that expand them will need relay settings, testing and commissioning support. Dominionโs Virginia grid data, cited above, offers a starting point for identifying where utilization is lowest and where this work could start.