A release on the Woodfibre LNG study credits construction with $13.6B in Canadian economic output. The project is about 75% complete, with completion expected in 2027.

FieldNews Staff|

Woodfibre LNG Claims $13.6B Output as Build Nears 75% Done

Woodfibre LNG in Squamish, B.C. is about 75% complete, with construction expected to finish in 2027. A release covered by the Journal of Commerce credits the build with nearly $13.6 billion in economic output across Canada.

The figures come from a study by Deetken Insight, a Canadian strategy and research firm. It covers construction and operation of the LNG facility and FortisBCโ€™s Eagle Mountain Pipeline. The source does not say who paid for the study, and the numbers are the projectโ€™s own claims, not independent findings.

The study estimates construction alone will generate:

  • Nearly $7 billion in GDP
  • $3.6 billion in labor income
  • More than 52,000 modelled employment-years
  • More than 15,000 direct and indirect jobs

Over construction and a 40-year operating period, the release projects about $11.6 billion in nominal government revenue. That includes roughly $6.8 billion for British Columbia and $485 million in municipal property taxes. The release also cites a $50 million cleanup of the former pulp mill site.

What It Means for Subcontractors

  • Late-stage scopes (our inference): With about 25% of the work left and completion due in 2027, remaining packages likely lean toward electrical and instrumentation, mechanical completion, commissioning support and punch-list closeout. The source does not list open scopes, so confirm with the contractors on site. E&I and insulation firms should ask about turnover walkdown schedules now.
  • Electrical emphasis: The facility is described as all-electric, so power and controls commissioning is central to completion. Electrical crews with energization and testing experience are the best fit.
  • Read the $13.6B carefully: It is modelled output across Canada, including the Eagle Mountain Pipeline and indirect effects. It is not contract value and not a pool of open subcontract work.

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

How to Promote Field Leaders Without Losing Your Best Hands: Foreman and Supervisor Development for Growing Subcontractors

Promoting your best hand to foreman is one of the most important decisions a subcontractor makes. Get it wrong and you lose two people: a skilled producer and a failed supervisor. This guide covers how to identify the right candidates, make the transition, and build a leadership pipeline that does not gut your field capacity.

Read the guide โ†’

More from British Columbia

All coverage โ†’
Follow FieldNews
A community project byAimsio