NYPA Shortlists 10 Developers for Up to 5 GW of New Nuclear
ENR reports the New York Power Authority (NYPA) has cut 21 applicants to 10 finalists for its push to add up to 5 GW of nuclear generation in the state before 2040, largely upstate.
Market Impact
NYPA said it will solicit proposals from one or more of the finalists for a specific project with a site and identified reactor technology. It gave no date beyond โthe coming months,โ per its Nov. 12 announcement. The agency plans to pick location and technology for the first 1 GW in the first half of 2027. Dates and scopes of the new solicitations will be confidential and covered by non-disclosure agreements, and NYPA said no public announcement will come until a project is selected.
Six finalists could build either a large reactor (about 1 GW) or a small modular reactor (about 300 MW): Avangrid, Elementl Power, NextEra Energy, Oppenheimer Energy, the Nuclear Co. and Turquoise Power. Four would develop only small reactors: Blue Energy, Holtec International, TerraPower and X-energy.
Eight communities have volunteered to host. They are Oswego County, Broome County, Jefferson County, Schuyler County, St. Lawrence County, Wayne County, the City of Dunkirk and Eastman Business Park in Rochester. Constellation Energy and the New York State Energy Research and Development Authority have filed a grant proposal with the U.S. Energy Dept. for an early site permit at Nine Mile Point in Oswego County.
The timing matters for the grid. The stateโs grid operator said Nov. 18 that New York faces a statewide resource deficiency of about 225 MW starting in 2033, growing to more than 1.85 GW by 2036. Gov. Kathy Hochul also released a 30-point nuclear โmasterplanโ and a policy white paper proposing cost controls, site and developer prequalification, and open-book negotiations to prevent overruns. Opponents cited by ENR argue the spending will not lower costs or decarbonize the grid quickly.
What It Means for Subcontractors
- Teaming comes first. With solicitations under NDA and no public notice until selection, the first look at scopes goes to the 10 finalists. Civil, mechanical and electrical subs should send capability packages to the finalistsโ supply chain contacts now, not after the 2027 site and technology pick.
- Civil and site work: Oswego County. Nine Mile Point is the site named in the filed federal early site permit grant proposal. Site prep and heavy civil firms near Oswego should position with Constellation and the developers likely to pursue it.
- Mechanical and piping: match the reactor type. Large reactors (about 1 GW) and SMRs (about 300 MW, or 80 MW units linked in groups of four for X-energy) mean different module sizes and repeat-build volumes. Pitch pipefitters and welders to the fleet-oriented developers, such as the Nuclear Co. (6-GW fleet target) and Elementl (five linked 300-MW reactors in its Ohio proposal).
- Electrical and E&I: grid timing. The grid operatorโs projected 2033 shortfall of 225 MW, rising past 1.85 GW by 2036, sets the schedule pressure. Expect interconnection and switchyard work to follow after the site and technology pick planned for the first half of 2027.
- Craft labor: use the training money. NYPA allocated the first $10 million of a $40 million fund, including $3.65 million to the Workforce Development Institute and the state Building & Construction Trades Council and $1.06 million to the Manufacturers Talent Institute. Contractors needing nuclear-ready crews should engage these groups on certifications and apprenticeship pipelines.
- Existing relationships help. Avangrid is the parent of NYSEG and Rochester Gas & Electric, so subs already on those utilitiesโ vendor lists have a head start on the Avangrid team.



