Judge Lets South32's $3.3B Arizona Mine Keep Building

A federal judge denied an injunction against South32's Taylor mine at Hermosa in southern Arizona. About $1B in growth capital is planned for fiscal 2027, but the underlying environmental case continues.

FieldNews Staff|

Judge Lets South32's $3.3B Arizona Mine Keep Building

A federal judge cleared the way for construction to continue at South32โ€™s $3.3 billion Taylor mine in Arizonaโ€™s Hermosa project, ENR reports, rejecting an injunction while an environmental challenge proceeds.

Market Impact

Senior U.S. District Court Judge Raner C. Collins in Tucson denied the injunction Nov. 6. He found the Patagonia Area Resource Alliance and Center for Biological Diversity had not shown likely irreparable harm from work expected before the court decides the underlying case. The groups allege deficiencies in the groundwater and endangered-species reviews and dispute the Forest Serviceโ€™s authority to approve some infrastructure on federal land. Collins also cited a โ€œsubstantial public interest in domestic critical-mineral supply.โ€

The ruling is not a final win. Collins said it does not โ€œvalidate every aspect of the Projectโ€ and ordered the parties to submit an expedited briefing schedule within 14 days of the ruling.

The project sits about 55 miles south of Tucson. South32 targets first production from Taylor in the second half of its 2028 fiscal year. It spent $197 million on Hermosa in the September quarter, extending the underground decline and sinking the main and ventilation shafts. All flotation cells and major electrical transformers are installed. Sundt Construction is construction manager at risk, and ENRโ€™s 2026 Top Contractors survey lists the $805 million Taylor process plant as Sundtโ€™s largest project to break ground in 2025. South32 plans another $1 billion in Hermosa growth capital in fiscal 2027.

What It Means for Subcontractors

  • Spending pace: $1 billion across fiscal 2027 (July 2026 to June 2027) averages roughly $250 million per quarter if spread evenly, above the $197 million spent in the September quarter. Underground, shaft and process-plant trades should expect volume to hold or rise.
  • Sundt is the buyer: As construction manager at risk, Sundt controls the Taylor process plant work. The source does not name open subcontract packages, so mechanical, electrical and process-plant subs should ask Sundtโ€™s Southwest team directly about remaining scopes.
  • Near-term federal-land work is small: South32 told the court that work on federal land over the next year is mostly geotechnical investigations, limited exploration drilling, previously disturbed areas and safety fencing. That fits geotech, drilling and fencing contractors. Larger civil scopes on the 423 acres of Coronado National Forest, including the access road, water infrastructure and haul roads, are likelier later.
  • Tailings facility is a 2028 story: The second tailings storage facility is not expected to start until 2028 and still needs engineering and state permitting. Earthworks and liner contractors should not expect bid packages before then.
  • Electrical: UNS Electric began the 138-kV transmission connection Sept. 8, with about 7 miles crossing federal land. Work could finish before the court rules, so line and substation crews have the clearest near-term window.
  • Schedule risk has eased, not ended: The partiesโ€™ expedited briefing schedule was due within 14 days of the Nov. 6 order, or roughly Nov. 20. That schedule will show how fast the merits case could move, which matters most for the federal-land scopes planned beyond the next year.

Sources

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

How to Promote Field Leaders Without Losing Your Best Hands: Foreman and Supervisor Development for Growing Subcontractors

Promoting your best hand to foreman is one of the most important decisions a subcontractor makes. Get it wrong and you lose two people: a skilled producer and a failed supervisor. This guide covers how to identify the right candidates, make the transition, and build a leadership pipeline that does not gut your field capacity.

Read the guide โ†’

More from Arizona

All coverage โ†’
Follow FieldNews
A community project byAimsio