Cheyenne Light Signs Microsoft Grid Deals as Wyoming Pipeline Hits 3 GW
Cheyenne Light has signed agreements to build distribution and transmission infrastructure for three Microsoft data centers in Wyoming, Utility Dive reports, and its 3-GW pipeline is about seven times its 439-MW peak load record.
Market Impact
The utility disclosed the agreements in a Nov. 24 filing at the Federal Energy Regulatory Commission. Microsoft pays for the infrastructure through โcontribution in aid of constructionโ payments. Cheyenne Light is a subsidiary of Bright Horizon Energy Corp., formed by the Nov. 13 merger of Black Hills Corp. and NorthWestern Energy Group. It doesnโt believe FERC has jurisdiction over the retail agreements but filed them anyway โout of an abundance of caution.โ
Company officials said on a Nov. 5 earnings call that the 3-GW pipeline includes 600 MW of Microsoft and Meta projects. The utility is also in initial talks on another 2.5 GW of early-stage opportunities. It serves about 46,000 retail customers and set its 439-MW peak in July.
The largest committed piece is Google. Cheyenne Light agreed in September to supply a Cheyenne data center with 590 MW and manage 2.1 GW of third-party power supply in a microgrid. To serve it, the utility plans a $1.8 billion, utility-owned 564-MW gas-fired plant built between 2027 and 2029 through an unregulated affiliate. The Google site is set to begin operating late next year and reach full load by the end of 2030.
Two proposed transmission projects totaling $686 million would serve large loads, including Google. Cost recovery depends on a proposed Large Customer Transmission Cost Adjustment Mechanism, and Black Hills expects a Wyoming Public Service Commission decision by mid-2027. Black Hills also warned of โsignificant uncertaintyโ in large load forecasts and of increased reliance on a single customer.
What It Means for Subcontractors
This quarter
- Electrical and line contractors in southeast Wyoming and northern Colorado: Ask Cheyenne Light directly about contractor prequalification for the Microsoft distribution and transmission work. The source names no EPC, GC, or bid date, so the utility is the first call. Read the FERC filing for scope clues, though the agreements are redacted.
- Civil and site crews: Microsoft funds the build-out through aid-of-construction payments. Our read, not the sourceโs: the utility likely manages these scopes, but confirm whether Microsoftโs own GCs hold any of the site work.
Next 12 to 24 months
- Transmission and substation trades: The $686 million in proposed projects is tied to the tariff, with a PSC decision expected by mid-2027. Our inference: package releases may follow that ruling. Pull the Wyoming PSC docket and note the date.
- Mechanical, pipefitting, and civil: The $1.8 billion, 564-MW gas plant runs 2027 to 2029 under an unregulated affiliate. That affiliate is a separate procurement path from the regulated utility, so ask Cheyenne Light which entity is buying. By our arithmetic, that is roughly $3.2 million per MW.
Position for later
- Treat the 2.5 GW as speculative. It is in โinitial talks,โ and Black Hills itself flags forecast uncertainty and single-customer exposure. Donโt staff up for it. Keep your prequalification paperwork current so you can move if those projects firm up.