B.C.'s $286B Project Pipeline: Only $32.5B Is Under Construction

A Greater Vancouver Board of Trade review of 47 B.C. major projects finds just 11% of the roughly $286 billion in value is under construction. Labour availability between 2027 and 2030 is flagged as the key risk.

FieldNews Staff|
Editorial image: industry general - B.C.'s $286B Project Pipeline: Only $32.5B Is Under Construction

B.C.'s $286B Project Pipeline: Only $32.5B Is Under Construction

Forty-seven major B.C. projects carry roughly $286 billion in potential capital investment, but only $32.5 billion of that is under construction today, according to a new Greater Vancouver Board of Trade (GVBOT) report covered by ReNew Canada. Another $120.6 billion is proposed, and the report warns that labor availability is becoming the main constraint as projects stack up between 2027 and 2030.

Background

The report, Delivering Growth: Realizing B.C.โ€™s Major Projects, is a one-year update to GVBOTโ€™s 2025 study. It reviews the 47 projects across clean energy, LNG, mining, trade infrastructure and other strategic sectors.

ReNew Canadaโ€™s summary of the findings includes:

  • $32.5 billion is already under construction.
  • $120.6 billion is in proposed developments.
  • LNG project investments could unlock a further $131.7 billion in upstream natural gas investment over the next 20 years.

GVBOT credits most of the past yearโ€™s policy progress to the federal government. It cites the Major Projects Office, the proposed Building Canada Strong Act, expanded Indigenous loan guarantee programs and new investment incentives. It rates progress on all three of its 2025 recommendations as โ€œStrongโ€ or โ€œGood-to-Strong.โ€ The report frames 2027 as a window for the incoming provincial government to act on its pledge to โ€œsuperchargeโ€ the economy.

Analysis

The split matters more than the headline. Here is the arithmetic on the sourceโ€™s figures. Projects under construction ($32.5 billion) are about 11% of the $286 billion total. Proposed developments ($120.6 billion) are about 42%. Together they come to $153.1 billion, or roughly 54%. That leaves about $132.9 billion, or 46%, that the source does not describe. Our read, not the sourceโ€™s, is that this is earlier-stage or otherwise uncategorized value. Treat it as even less certain than the โ€œproposedโ€ bucket.

The $131.7 billion in upstream gas investment is described as additional to the project figures. It is a 20-year number and depends on LNG decisions that have not been made.

The crunch is a sequencing problem. The report says multiple major projects are expected to advance at once, particularly from 2027 to 2030, and that labor is an emerging risk. GVBOT is calling for coordinated workforce planning for skilled trades and technical workers. The source does not say which trades are tightest, and it does not give a headcount. Our inference is that the squeeze will be felt first by whichever trades the projects under construction already use, and that every proposed project reaching a final investment decision adds to it.

Several approvals and conditions are still unresolved. GVBOT will track whether the province delivers the following:

  • The promised 120-Day Permitting Act, for projects over $250 million, with transparent reporting on approval times.
  • A natural gas growth plan and a competitive royalty framework, before the next round of LNG investment decisions.
  • PST relief on major project construction and on machinery, equipment and software, in its first budget.
  • Faster Indigenous participation and more certainty in the legal framework.
  • Published grid connection timelines.

From Ottawa, GVBOT will track passage of Bill C-39 and on-time federal milestones for Pacific Link, Roberts Bank Terminal 2 and Trans Mountain Mainline Optimization. The source does not say which of these are under construction, and it gives no budget date or bid schedule for any of them.

The $250 million permitting threshold also leaves out smaller work. Mid-size packages would not get the 120-day clock if the act passes as described.

What It Means for Subcontractors

Next two quarters (Q4 2026 to Q1 2027): live work and crew capacity

  • Size the real near-term market at $32.5 billion, not $286 billion. That is the only portion the report confirms is in construction. The source does not name the individual projects, owners or EPCs behind it, so ask GVBOT for the project-level list in the full report. Match it against your own trades and territories before committing to bids.
  • Plan crews for 2027 to 2030 now. The report flags that period as the labor-risk window. If you run civil, electrical, mechanical or industrial crews in B.C., decide this quarter whether to lock in apprentices and key hires, because the source offers no workforce plan or timeline for relief.
  • Do not assume open scopes on projects already underway. The source says nothing about which packages remain unawarded. If you want in, ask owners or GCs directly whether any scopes are still open, and expect little on the largest awarded jobs.

Position for 2028 and later: conditional work

  • Treat the $120.6 billion proposed bucket as pipeline, not backlog. It depends on approvals, financing and the policy items above. Start relationship work with likely owners, but do not add overhead against it.
  • Mark three triggers on your calendar. They are passage of the 120-Day Permitting Act, publication of the natural gas growth plan with a royalty framework, and the provinceโ€™s first budget (no date given). The LNG-linked upstream work, with its $131.7 billion potential over 20 years, is gated by the royalty decision.
  • Price in the PST change, but do not bank it. PST relief on construction and on machinery, equipment and software is promised for the first budget. Our read: if it lands, equipment purchase timing and bid pricing could shift. Until the budget is delivered, hold fleet and tooling decisions to your normal criteria.
  • Federal milestones are the earlier signals. Watch Bill C-39 and the on-time milestones for Pacific Link, Roberts Bank Terminal 2 and Trans Mountain Mainline Optimization. Any slip on those would likely push related subcontract timing to the right.

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

From the Field to the Office: What Oilfield Workers Should Know Before Making the Switch

Thinking about moving from field work to an office role? This guide covers how your field experience translates into technical and operations positions, what the transition actually looks like, and the trade-offs most people do not talk about until it is too late.

Read the guide โ†’

More from British Columbia

All coverage โ†’
Follow FieldNews
A community project byAimsio