Bally's Halts Chicago Hotel Work, Idling 1,500 Trades in Gaming Dispute
Construction on the hotel tower at Ballyโs $1.7 billion Chicago casino complex has stopped after the company ordered its contracting team to stand down, ENR Midwest reports, citing a fight with the city over video gaming terminal legalization that has idled 1,500 union trade workers.
Market Impact
Ballyโs issued the stop-work notice Aug. 8 to the Chicago Community Builders Collective, the contracting partnership building a 34-story hotel, restaurants, and an events center as part of the River West project. The company says Chicagoโs decision to lift its ban on video gaming terminals, effective Jan. 1, 2026, violates a commitment in its Host Community Agreement not to expand gaming in the city and could undercut the casinoโs business. Ballyโs has hired law firm RKF Global and is weighing withholding a $4 million annual payment to the city thatโs due in September, arguing โthe city has breached the [host agreement] and we are not obligated for payment,โ according to spokesperson Lauren Westerfield.
The stakes go beyond the hotel job. Chicago has estimated the full casino complex will generate roughly $200 million a year in local tax revenue, while the city is counting on video gaming licensing citywide to bring in $6.8 million to help close a budget shortfall. Illinois Gaming Board figures show video terminals statewide pulled in about $532 million in revenue between January and July 2026, compared to nearly $222 million from casinos, underscoring why Ballyโs sees terminal proliferation as a direct threat. Ballyโs says the casino itself is still targeted to open in early 2027 and that it intends to honor its commitments under the agreement, even as hotel and amenity work sits idle. This isnโt the projectโs first stoppage: the gaming board ordered a stop-work in May 2025 over an unauthorized waste hauler with alleged organized crime ties.
What It Means for Subcontractors
- Trade contractors on the Chicago Community Builders Collective team, including Gilbane Building Co., Brown & Momen, dโEscoto, LiveWire Construction, Milhouse Engineering & Construction, Powers & Sons, UJAMAA Construction, Riteway-Huggins, and SQN Associates, should confirm lien rights now given Ballyโs is openly disputing payment obligations to the city.
- Subs should re-price float into any remobilization schedule tied to the disputed hotel, restaurant, and events center scope; the casinoโs early 2027 opening target does not guarantee the non-gaming work resumes on the same timeline.
- With 1,500 union tradespeople idled, GCs should document idle-time and standby costs now, before renegotiating schedule and payment terms once Ballyโs and the city resolve the video gaming dispute.