SpaceX Appears to Land First Texas Data Center Permit Post-Freeze
The first Texas data center permit issued since the stateโs freeze lifted appears to have gone to SpaceX for a $24 billion Starbase project, OilPrice.com reports, citing Politico.
Market Impact
The Texas Commission on Environmental Quality (TCEQ) returned to normal permit review on Nov. 16. The agency had been told ERCOT finished gathering community-impact information for its audit. Gov. Greg Abbottโs September letter tied the pause to that audit, and ERCOTโs reports are not targeted until Dec. 10. Gibson Dunnโs calendar lists Dec. 17 for the Public Utility Commissionโs meeting on them. The restart came weeks early.
The freeze began in August, when Abbott effectively halted new data center grid connections. In September he told TCEQ to stop issuing air and other permits for the same projects. Within days, the agency mailed preliminary approvals for three gas-fired power projects meant to supply data centers, according to a FracTracker and Public Citizen report cited by OilPrice.com. Abbottโs press secretary, Andrew Mahaleris, said, โNo permits have been approved.โ
The demand picture is cloudier than the headline numbers. ERCOTโs large-load queue stands at 474 GW, more than five times the gridโs all-time peak of a little over 90 GW. PUC Chair Thomas Gleeson has said โa lot of that load will not actually come here.โ Senate Bill 6 now requires applicants to prove site control, cover most grid upgrade costs and accept curtailment in emergencies. Hinojosa has also promised a pause of her own after taking office Jan. 19.
Our read, not the sourceโs: the SpaceX permit shows TCEQ is processing again, but ERCOTโs Dec. 10 reports and the Dec. 17 PUC meeting look like the real gates. Expect permits in batches, not a flood.
What It Means for Subcontractors
This quarter
- Starbase civil and site-prep: The source names no GC, scopes or bid dates for the $24 billion project. Contact SpaceXโs procurement team directly with your capabilities rather than waiting for a package to surface.
- Gas-fired power scopes: The three projects have preliminary approvals only, and the governorโs office says nothing is approved. Do not mobilize crews or order long-lead pipe, switchgear or generation equipment until the client confirms a final TCEQ permit.
- Dec. 10 and Dec. 17: Ask clients on data center work whether they have filed ERCOT audit information and how they expect the PUC meeting to affect schedules. Build schedule-slip language into any bid priced before those dates.
Position for later
- Payment risk: SB 6 forces applicants to show site control and fund most grid upgrades. Projects that clear it should be better capitalized, which is our inference. Ask for proof of both before extending credit.
- Abilene housing: Rents there are up nearly 50% in a year to about $2,600 a month. Taylor County has approved thousands of housing units and RV spaces. Price per diem and lodging into West Texas bids.
- Jan. 19 and the queue: Hinojosa has promised a pause after taking office. With the 474 GW queue largely hypothetical, staff only for projects with a named power source and customer. Abileneโs Stargate campus had six of eight buildings delivered by Sept. 10, per Oracle.