Pentagon Has 400 Onshore Wind Projects Waiting on Eight Reviewers
About 400 onshore wind projects are waiting on a Pentagon review queue handled by eight federal employees, Utility Dive reports, citing a Nov. 3 court filing from a senior DOD official.
Dale Marks, assistant secretary of defense for energy, installations, and environment, made the statement in the U.S. District Court for the District of Oregon. The filing responds to a lawsuit from clean energy trade groups, developers and states. Their May 31 complaint alleges DOD stopped assessing wind projectsโ impacts on military readiness.
Market Impact
Marks said none of the teams reviewing wind permits are sized for the surge of applications in recent years, a period that also saw pressure on manning, funding and contractor support. Contractors cannot perform inherently governmental functions, he wrote, so action on the roughly 400 projects rests โsolelyโ with eight federal employees.
DOD typically executes 13 mitigation agreements in an average year, Marks said, and recently about 30. DOD says it is complying with an August court injunction staying what it calls a โtemporary pauseโ and has returned to reviewing permits.
The American Clean Power Association disputes that. In an Oct. 20 declaration, Vice President Tom Vinson said DOD โhas not resumed reviewโ and that none of its administrative activity has produced substantive movement through mitigation review. He cited one project whose turbine delivery was pushed back. Equipment delivered after Dec. 31, 2027 will not qualify for the Advanced Manufacturing Credit, worth about $200,000 per turbine, or roughly $24 million for that project, per the developerโs estimate. That math implies about 120 turbines.
Plaintiffsโ reply to DODโs filing is due Nov. 17. The source does not name the affected projects or their regions, and it gives no public timeline for clearing the queue.
What It Means for Subcontractors
- Tower, foundation and crane subs: Treat any 2027 start tied to a project awaiting DOD clearance as unconfirmed until it clears review. The source does not identify which projects are in the queue, so ask your GC or developer client directly whether a given site has an open DOD review.
- Collector-line and civil crews: Developers with a Dec. 31, 2027 turbine-delivery cutoff for the Advanced Manufacturing Credit may compress site work if clearance arrives late. Hold crew and equipment availability flexible for late-2027 mobilizations rather than committing to fixed windows.
- Backlog math, as an inference: At 13 agreements a year, 400 projects would take about 31 years. At the recent pace of about 30, it would take about 13. Not every project necessarily needs a mitigation agreement, and the source does not say how many do. Still, the numbers argue against assuming a quick clearance.
- Contract terms: Where you hold or are bidding wind subcontracts, check for notice-to-proceed dependencies and standby or demobilization language tied to federal permitting. Do this soon, since a court ruling on enforcement of the injunction, which could follow the Nov. 17 plaintiffsโ reply, may change timing.
- Backfill planning: With the queue size and the eight-person staffing level both on the record, subs with heavy wind exposure should line up non-wind work for 2027 gaps, such as transmission or solar civil and electrical scopes.