FieldNews
Subscribe

Daily oil & gas and construction news for subcontractors

Invenergy Files for 345 kV Line to Serve 300 MW Bodark Solar Near Muskogee

Invenergy's roughly $160 million, 300 MW Bodark solar project near Muskogee has an Oklahoma Corporation Commission filing for a 6.7-mile, 345 kV interconnection line. Construction is planned for 2027 through 2029.

FieldNews Staff|

Invenergy Files for 345 kV Line to Serve 300 MW Bodark Solar Near Muskogee

A roughly $160 million, 300 MW solar project near Muskogee has moved to the Oklahoma Corporation Commission, and it brings a $20 million, 6.7-mile transmission line with it. OK Energy Today reports that Invenergyโ€™s Bodark Solar Energy Center is seeking a certificate of authority (docket 2026-000086) for a double circuit, 345 kV above-ground line tying into Oklahoma Gas & Electricโ€™s Pecan Creek substation.

The developer is funding both the plant and the line. Because Bodark is not a public utility, it cannot recover costs through rates. Construction is planned to start in 2027 and finish in 2029, per the filing. Seven private landowners have signed contracts, and the footprint could reach 4,000 acres or more (an estimate, since the filing gave no acreage figures).

Invenergy filed โ€œout of an abundance of caution,โ€ noting it is unclear whether the High Voltage Electric Transmission Facility Act covers a line this short. The company projects up to $589.3 million in in-state spending over the facilityโ€™s 30-year life.

What It Means for Subcontractors

  • No bid stage yet. The next gate is the Corporation Commissionโ€™s action on docket 2026-000086. The source gives no hearing date and names no EPC or construction contractor, so packages are unlikely before approval.
  • Line scope is about $20 million. That covers 6.7 miles of 345 kV double circuit, which likely means foundations, structure setting, and stringing work for transmission crews (our inference, since the source does not list scopes). A 2027 start leaves the procurement window after the commission ruling.
  • Site work could be large. On 4,000 or more acres across seven landowners, civil, pile-driving, and electrical collection scopes are the likely trades (our inference, since the source does not list scopes). Construction runs 2027 to 2029.

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

Mechanic's Lien Rights for Subcontractors: What to Do When You're Not Getting Paid

A practical guide to mechanic's lien and materialman's lien rights for oilfield and construction subcontractors in Texas, Oklahoma, and Alberta โ€” deadlines, filing steps, and leverage tactics.

Read the guide โ†’

More from Oklahoma

All coverage โ†’
Follow FieldNews
A community project byAimsio