OG&E Breaks Ground Nov. 16 on $506M Horseshoe Lake Expansion
OK Energy Today reports that Oklahoma Gas and Electric will break ground Monday, Nov. 16, on Units 13 and 14 at its Horseshoe Lake Power Plant east of Oklahoma City, part of more than $800 million in new generation.
Market Impact
The ceremonies start at 10 a.m. Monday. OG&E will cut the ribbon on two completed natural gas-fired units, Units 11 and 12, and then break ground on the next two. The company says the events mark a new chapter in Oklahomaโs energy infrastructure.
Units 11 and 12 cost $330.5 million, according to the utility. Together they add about 448 megawatts of capacity, enough to power roughly 300,000 homes. They replace two units that served customers for more than 60 years. Units 13 and 14 carry a total price of $506.4 million. Adding the two phases gives $836.9 million, which matches the โmore than $800 millionโ figure. OG&E has not released a capacity figure, schedule or contractor list for Units 13 and 14.
The pattern here is a utility replacing aging generation at an existing site in phases. The first phase is finished, and the second is just starting.
What It Means for Subcontractors
- Civil and foundations: A groundbreaking usually means site prep and foundation work come first. With $506.4 million committed to Units 13 and 14, civil firms in the Oklahoma City metro should find out this week who holds the construction contract and when earthwork and concrete packages go out.
- Mechanical and piping: Units 11 and 12 are natural gas-fired, and Units 13 and 14 are expected to be similar generation. Pipefitters, welders and mechanical contractors should ask OG&Eโs supply chain group and the lead contractor how piping and equipment-setting scopes will be bid.
- Electrical and interconnect: Electrical, instrumentation and controls firms should ask the same question for cable, termination and tie-in work, since the units must connect to the existing plant. Ask for the name of the package owner and a bid date.
- Supplier registration: OG&E has not named a prime contractor in this announcement. Call OG&Eโs procurement team and ask whether supplier registration is required, then complete it before year-end so you are on lists when packages open.
- Use Units 11 and 12 as a reference: That $330.5 million phase just finished at the same site. Contractors who worked it should contact the same project managers now. Firms that did not can use the completed phase as a benchmark for scope and pricing when they approach Units 13 and 14.
- Equipment and OEM packages: OG&E has not named any equipment suppliers. Ask OG&E or the lead contractor which OEMs are supplying the units, because their field service and erection subcontracts often sit outside the main bid list.
For updates, check OG&Eโs announcements after Mondayโs ceremony for the lead contractor and schedule.