Bot Construction Starts Highway 10, Bovaird Bridges Over Hwy 413
Construction has started on two Highway 413 bridges at Highway 10 and Bovaird Drive in Brampton, Ont., with Bot Construction Limited awarded the contract, per a Daily Commercial News report dated November 16, 2026.
Market Impact
The Ontario government says the two structures will carry Highway 10 and Bovaird Drive traffic over the future Highway 413. At Highway 10, crews will build a new bridge over the future highway. The Bovaird Drive package is larger. It includes a bridge over the highway, widening of Bovaird Drive, and a grade separation from Heritage Road to Mississauga Road. That work prepares the corridor for a future interchange at Highway 413. The release does not give a contract value or schedule.
The province also recently issued a Request for Proposals (RFP) to design and build the eastern section of Highway 413, from Highway 400 to west of The Gord Road. The RFP also covers extending Highway 427 from Major Mackenzie Drive north to Highway 413.
Once complete, Highway 413 will run from Highway 400 in the east to the Highway 401/407 ETR interchange in the west. It will have 11 interchanges at municipal roads, plus connections to Highways 410 and 427. The province says construction will support approximately 6,000 jobs annually.
What It Means for Subcontractors
- Structural concrete, rebar, formwork and piling: Bot Construction Limited holds the contract and work has started on two bridge structures. Contact Botโs estimating team now, before the bridge packages are fully subbed out.
- Civil, paving, traffic control and utility relocation: The Bovaird Drive package includes widening and a grade separation between Heritage Road and Mississauga Road. Roadwork, staging and relocations around that stretch are the likely sub scopes. Pitch Bot directly for them.
- Design-build RFP teams: The eastern section (Highway 400 to west of The Gord Road) and the Highway 427 extension north from Major Mackenzie Drive are in the RFP stage. Proponent teams will be lining up subs and suppliers while they price. Check the Ontario MTO and Infrastructure Ontario procurement pages for the RFP documents and the list of interested teams. Then get your qualifications to those teams before they submit.
- Interchange and grade-separation trades: The finished highway has 11 municipal interchanges, and the Bovaird work is early prep for one of them. Bridge, retaining wall, drainage and grading contractors should treat this as a multi-package pipeline. Use the Bovaird scope to build a track record with Bot ahead of later packages.
- Workforce planning: The province projects about 6,000 jobs annually during construction. Labor will be contested across the corridor, so lock in crews, equipment and certifications now if you plan to bid more than one package.