Yukon Energy Fires Prime on $35M Whitehorse Battery Project

Yukon Energy dismissed SunGrid Solutions and is taking over as prime contractor on its delayed $35 million battery storage project in Whitehorse. Completion has slipped from 2023 to 2027.

FieldNews Staff|
Editorial image: Stalled night battery construction site - Yukon Energy Fires Prime on $35M Whitehorse Battery Project

Yukon Energy Fires Prime on $35M Whitehorse Battery Project

Yukon Energy has fired SunGrid Solutions as prime contractor on its $35 million Whitehorse battery storage project and will take over the prime role itself, a Canadian Press report via Journal of Commerce says.

Market Impact

The project was supposed to be finished in 2023. Yukon Energy says SunGrid failed to reach โ€œsubstantial completionโ€ within its contracted time frame, and the system is now expected to come online in 2027. Construction began in April 2022 on Kwanlin Dun First Nation Settlement Land in Whitehorse. The battery is meant to help the territory handle peak winter power demand. When finished, the utility says, it will be the largest grid-scale battery storage system in the North and one of the largest of its kind in Canada.

Ottawa is contributing about $16.5 million, and Yukon Energy is covering the rest. By our math, that leaves roughly $18.5 million on the utilityโ€™s side. The utility says it is pursuing โ€œdamages and other remediesโ€ under the terminated contract, but adds that this does not mean it will start legal proceedings. SunGrid did not immediately respond to a request for comment.

Paul Murchison, Yukon Energyโ€™s vice-president of capital projects, said the utility โ€œcarefully considered the challenges, the work remaining and the options available to us.โ€ He said the change gives the project the best path to finishing โ€œsafely and responsibly.โ€ Yukon Energy Minister Ted Laking said the utility has been directed to run an independent review of procurement and lessons learned, and that the results will be made public. The source gives no date for that release.

What It Means for Subcontractors

The source does not say which subcontractors are on site, how their agreements are being handled, or whether any work will be re-tendered. The points below are our read, not the sourceโ€™s.

This quarter

  • Confirm your contract position now. If you hold a subcontract under SunGrid on this job, ask Yukon Energyโ€™s capital projects office (Murchisonโ€™s group) in writing whether your agreement will be assumed, replaced or terminated. Do this before you demobilize or add more work.
  • Document unpaid and completed work. Pull progress billings, approved change orders and delivery records. Have contract counsel check your lien and notice deadlines under the applicable Yukon legislation. The source does not say whether SunGrid has outstanding payables.
  • Do not assume the new prime will honor old terms. Yukon Energy says it is taking over as prime, but it has not said it will adopt SunGridโ€™s subcontracts. Get any continuation of scope, rates or schedule confirmed before you commit crews.

Later

  • Position for remaining scope before the 2027 online date. Yukon Energy says it weighed โ€œthe work remaining,โ€ so some scope is evidently left. Trades typically involved in battery storage installs, such as electrical, E&I, civil and commissioning support, should make themselves known to the utility directly. The source names no packages or bid dates.
  • Read the procurement review when it is released. No date is given. It may change how Yukon Energy structures prime contracts and subcontractor oversight on future territorial energy projects.
  • Watch for a damages claim. If Yukon Energy pursues SunGrid, subs may be asked for records or testimony. Keep your project files organized.

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

How to Hire and Retain Field Workers Without Raising Pay: The Complete Guide

Losing crew to competitors over small pay differences? Struggling to hire in a tight labor market? Here are the recruiting, onboarding, and non-wage retention strategies that actually keep oilfield and construction field workers from walking.

Read the guide โ†’

More from Yukon

All coverage โ†’
Follow FieldNews
A community project byAimsio