Trump Administration Appeals Ruling Blocking Hudson Tunnel Funding Freeze
The Trump administration filed an appeal Aug. 28 challenging a federal court judgment that bars the U.S. Department of Transportation from withholding funding for the $16-billion Hudson Tunnel Project, Engineering News-Record reports. Payments and construction continue while the case proceeds.
Market Impact
The Justice Departmentโs notice, filed in the Southern District of New York, appeals a June 30 final judgment by U.S. District Court Judge Jeannette Vargas. Vargas had ruled that DOTโs Sept. 30, 2025, suspension of grant disbursements violated federal regulations and permanently barred the agency from relying on that suspension to withhold future payments. DOT had cited a review of the Gateway Development Commissionโs disadvantaged business enterprise program but never made a formal finding of a violation.
The funding freeze previously forced the commission to halt construction on Feb. 6 after exhausting available funding and credit, a stoppage that affected nearly 1,000 workers. Work resumed later that month after Vargas temporarily blocked the suspension and DOT released about $205.3 million in withheld payments. A separate Court of Federal Claims case found DOT failed to follow required procedures under six grant and loan agreements worth roughly $14.7 billion before suspending payments. The commission said Sept. 1 that the new appeal โhas not disrupted federal reimbursements,โ with spokesperson Molly Beckhardt telling ENR the agency โhas received all reimbursements on the schedule established in GDCโs federal funding agreements with our federal partnersโ since February. New Jersey Gov. Mikie Sherrill and New York Gov. Kathy Hochul called the June ruling a victory and pledged to keep defending the project. Six of the projectโs 10 construction packages are completed or underway, including a $1.29-billion tunnel-boring contract awarded to a Traylor Bros.-Walsh Construction-Skanska USA Civil joint venture.
What It Means for Subcontractors
- Crews on active packages, including the Traylor Bros.-Walsh-Skanska joint venture boring the Hudson River tunnel section, should confirm with the Gateway Development Commission or their GC that reimbursement schedules remain unchanged given the new appeal filed Aug. 28.
- Subs on the remaining four construction packages not yet underway should ask GCs for a firm notice-to-proceed timeline, since a prior funding freeze in September 2025 already forced a full stoppage affecting nearly 1,000 workers before it was reversed in February.
- Firms holding contracts tied to the six grant and loan agreements totaling $14.7 billion should request written confirmation from the commission of current payment status before year-end, given a federal court already found DOT failed to follow required disbursement procedures once.
- Payroll and cash-flow planners should build in contingency for a possible funding pause if the appeals court sides with DOT, since the June 30 judgment barring withholding is now under active challenge rather than final.
- Subs should track the case in the federal appeals court in New York City for a ruling date, since no schedule was disclosed and a reversal could reopen the same reimbursement risk seen last year.



