IndustryOhio2 min read

Cleveland-Cliffs' $1B Middletown Works Overhaul Locks In $500M DOE Grant

Cleveland-Cliffs finalized a $500 million DOE grant framework to fund a $1 billion blast furnace and cogeneration upgrade at its Middletown Works steel plant, with construction employing 1,500 workers at peak.

FieldNews Staff|
Editorial image: Steel plant blast furnace retrofit aerial - Cleveland-Cliffs' $1B Middletown Works Overhaul Locks In $500M DOE Grant

Cleveland-Cliffs' $1B Middletown Works Overhaul Locks In $500M DOE Grant

Cleveland-Cliffs announced that the U.S. Department of Energy has established a framework to finalize a rescoped $500 million grant supporting a $1 billion optimization of the companyโ€™s Middletown Works steel plant in Ohio, the company said in a press release. Funding is split evenly between Cliffs and the DOE, with the multi-year project set to begin within weeks and the blast furnace rebuild targeted for completion in the first quarter of 2030.

Market Impact

The DOE grant was originally awarded in March 2024 to help replace Middletown Worksโ€™ coal-fired blast furnace with hydrogen-ready and electric furnace technology. Under the finalized framework, Cliffs will instead refurbish and upgrade the existing 73-year-old blast furnace rather than replace it, alongside advanced material handling infrastructure and artificial intelligence-enabled process controls. A central piece of the project is a new cogeneration facility that will capture blast furnace gas to generate on-site electricity and steam, cutting reliance on external power and lowering operating costs.

Vice President J.D. Vance visited the plant in his hometown of Middletown, Ohio, alongside U.S. Secretary of Energy Christopher Wright and state officials to mark the announcement. Cliffs Chairman and CEO Lourenco Goncalves said the project โ€œgoes above and beyond a standard blast furnace relineโ€ and preserves 2,300 jobs at the facility, which produces roughly 3 million tons of raw steel annually for automotive-grade sheet applications.

What It Means for Subcontractors

  • At peak construction, the project will employ more than 1,500 workers including local union building trades, a large multi-year mobilization for mechanical, E&I and structural contractors in the Middletown, Ohio area.
  • The new cogeneration facility is a standalone construction scope beyond the blast furnace reline, likely opening separate subcontract packages for power generation and gas-handling equipment installation.
  • With the blast furnace rebuild targeted for Q1 2030 completion, this is a multi-year program, giving contractors a long runway to plan crew allocation and long-lead equipment procurement.
  • AI-enabled process control and advanced material handling upgrades signal instrumentation, controls and automation subcontractors should expect scope alongside the traditional heavy-industrial trades on this job.

Get The Field Report

The week in oil & gas and heavy construction โ€” market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

From the Field to the Office: What Oilfield Workers Should Know Before Making the Switch

Thinking about moving from field work to an office role? This guide covers how your field experience translates into technical and operations positions, what the transition actually looks like, and the trade-offs most people do not talk about until it is too late.

Read the guide โ†’

More from Ohio

All coverage โ†’
Follow FieldNews
A community project byAimsio