Data Center Subs: Lock Down Coverage Before Ground Breaks
Large power transformers are running three to five years out, and about 40% of planned U.S. data center capacity is delayed, mostly over equipment shortages. Craig Tappel, a construction insurance broker, argues in Construction Executive that those delays make early insurance structuring a competitive issue for contractors. He says MEP scopes carry the largest concentration of risk and strain contractorsโ surety and insurance capacity.
What It Means for Subcontractors
- Surety and default exposure: The article says project values are rising faster than the surety market can bond them, and owners and GCs should consider requiring subcontractor bonds or SDI on critical-path scopes. Ask your broker now how much bonding capacity you have for a data center MEP package. Also ask whether a GC could require SDI instead. A default replacement could take months, so expect scrutiny.
- Builders risk and liability fit: Ask whether the projectโs builders risk includes testing and commissioning extensions and delay-in-completion/soft cost coverage, and whether limits match phased turnover. Check whether a contractor-controlled insurance program is in play, and what it means for your own limits. Tappel says standard CGL forms donโt cover construction-phase cyber exposure, such as networked building automation systems. Ask about that gap too.
- Pollution and new hazards (our read, not the sourceโs): The source doesnโt detail pollution limits. It does flag environmental closeout as a gap in standard operational policies, along with diesel fuel systems and liquid cooling hazards. Ask your broker whether your pollution limits meet the GCโs contract requirements. For 800V DC work, the article says arc flash and electrocution risks donโt fit neatly into existing OSHA standards. Underwriters also want to see data center loss history and proof you arenโt growing too fast.