Black Bayou Starts Construction on 44.4 Bcf Louisiana Gas Storage Hub

Black Bayou Energy Hub began site work Nov. 11 on a FERC-certificated, four-cavern gas storage facility in Cameron Parish, Louisiana. First caverns are targeted for late 2028, with 1,000+ construction jobs at peak.

FieldNews Staff|
Editorial image: Aerial gas storage site prep - Black Bayou Starts Construction on 44.4 Bcf Louisiana Gas Storage Hub

Black Bayou Starts Construction on 44.4 Bcf Louisiana Gas Storage Hub

According to a Nov. 13 company release, Black Bayou Gas Storage, LLC has begun construction on its natural gas storage project in Cameron Parish, Louisiana. Site work started Wednesday, Nov. 11, shortly after the Federal Energy Regulatory Commission issued a Limited Notice to Proceed on Oct. 20.

What Is Being Built

The project sits on a 2,500-acre site on the Black Bayou salt dome, which the company says it controls in its entirety. The initial phase is four caverns with 44.4 Bcf of FERC-certificated working gas capacity. A dual-header pipeline system will connect the facility to 13 interstate pipelines.

The certificate allows up to 1.6 Bcf/d of injection and 2.0 Bcf/d of withdrawal. The company says it will offer high-deliverability, multi-cycle storage, balancing, wheeling and blending services to LNG export terminals, local distribution companies, power generators, marketers and producers. Initial in-service is targeted for late 2028.

โ€œWith our FERC approvals in hand, we have moved from planning to building,โ€ said Tad Lalande, CEO of Lafayette-based Black Bayou Energy Hub. Daniel James, SVP Development, said the focus now is on โ€œexecuting the work safely and efficientlyโ€ and on working alongside contractors, local partners and surrounding communities as construction progresses.

Jobs and Schedule

The company expects more than 1,000 construction jobs at peak, plus 23 direct and 35 indirect permanent jobs in Louisiana, for a total of 58 potential new positions. The release does not name an engineering, procurement or construction contractor, and it does not give a project cost.

What It Means for Subcontractors

  • Early site work: Construction is under way, so site preparation, access roads, laydown areas and drainage packages are the first scopes likely to be let. Local civil and earthwork firms in Cameron and Calcasieu parishes should ask Black Bayou who is managing procurement.
  • Pipeline and header work: A dual-header system tied into 13 interstate pipelines points to substantial piping, welding, hydrotesting and tie-in work. Pipeline crews with Gulf Coast experience should watch for those packages.
  • Compression and electrical: Injection of up to 1.6 Bcf/d and withdrawal of up to 2.0 Bcf/d implies compression, power and controls scopes. Confirm lead times with suppliers early, because a late 2028 in-service date leaves limited slack.
  • Staffing: A peak workforce above 1,000 will draw on the same Gulf Coast labour pool as nearby LNG and industrial projects. Firms that need welders, electricians or equipment operators should line up crews well ahead of the peak.
  • Who to call: The release does not name a general contractor, so start with Black Bayou Energy Hubโ€™s development team in Lafayette.

Get The Field Report

The week in oil & gas and heavy construction: market data, the big story, and where the work is. Every Sunday, in 60 seconds.

Your regions (up to 3)

Free, no spam, unsubscribe anytime.

๐Ÿ“˜

Want the full picture?

From the Field to the Office: What Oilfield Workers Should Know Before Making the Switch

Thinking about moving from field work to an office role? This guide covers how your field experience translates into technical and operations positions, what the transition actually looks like, and the trade-offs most people do not talk about until it is too late.

Read the guide โ†’

More from Louisiana

All coverage โ†’
Follow FieldNews
A community project byAimsio