Highway 995 Nears Completion in Saskatchewan, Little Left to Bid
Saskatchewanโs 102-kilometre Highway 995 is entering its final construction stage, with completion set for 2027, the Journal of Commerce reports. The gravel road will give Wollaston Lake and Hatchet Lake Denesuline First Nation year-round access.
Market Impact
The road replaces a seasonal 50-kilometre ice road. For much of the year, residents rely on air transport or water barge, which limits timely delivery of essential goods, according to the release carried by the Journal of Commerce (DCN-JOC News Services).
Hatchet Lake Denesuline First Nation and its contractor will keep operating the road until construction wraps up in 2027. After final inspections, the Saskatchewan Ministry of Highways will take over operation and maintenance.
Planning and design began in 2004. Indigenous Services Canada has put in just over $70.3 million to date. The Ministry of Highways added $250,000 at the start of the current project, plus $10.1 million for the first 14 kilometres between 2007 and 2011. By our math, those named contributions total roughly $80.7 million.
Separately, Ottawa announced $1.3 million through the Direct Delivery stream of the Build Communities Strong Fund for phase one of a landfill upgrade in the community. Phase one covers:
- A new municipal waste storage cell sized for 10 years of municipal solid waste
- A leachate collection system
- A stormwater pond
- Operating stations
- Capping and closing the existing landfill
What It Means for Subcontractors
- Road construction: Little remains to bid. The source names no contractor, open packages, or bid dates, and the job is in its final stage. Only sub-trades already working under the prime are likely to see remaining scope.
- Landfill phase one: This is the most active opportunity, though timing is unconfirmed. Earthworks, liners, drainage, and civil crews should ask the community office for procurement details. The source does not say who is delivering the work or when it will be tendered.
- Landfill closure scope: Capping and closing the existing landfill is a separate scope from building the new cell. Earthmoving and cover-system contractors should ask whether it is bundled with the new cell or packaged separately.
- After 2027: The Ministry of Highways takes over operation and maintenance after final inspections. Our read, not the sourceโs: gravel highway maintenance such as grading, culverts, and snow clearing could become a recurring opportunity. Ask the ministry how it plans to handle upkeep.
- Remote logistics, our inference: A year-round road changes how crews and materials reach the area, replacing the winter-only ice road and barge or air freight. Contractors should price future work with that in mind, but should not assume costs fall until the road is inspected and open.
- Later phases: The word โphase oneโ implies more landfill work could follow, but the source gives no schedule or funding for later phases. Keep this on a longer-term list.